 
 
 
 
 
 
 
 
 
 
 
 
    
        Progress of LNER Brake Pigeon Van 70759  -  2012
 
 
    
        January  2012
    
        The transformation of BG(P) 70759 into a Brake 3rd (BTK) began with the re-panelling interior of the luggage
        end using the original planks after many hours of paint removal, hole plugging and repairs, two sections have
        been completed on the town side and enough planks have been prepared for one section on the railway side.
        
    
        The construction of the first section of the new side framing for the passenger section has been progressing.
 
 
 
 
    
        First section (known as T1) panelled just waiting
    
        for the lower plank and bottom rail.
 
 
    
        T2 panelling well underway. note the additional
    
        brake setter pipe.
 
 
    
        The construction of the first section of frames
    
        for the passenger end well underway. 
 
    
        March 10th  2012
    
        The working platforms and access steps were repositioned ready for the fitting the first section of the new
    
        passenger frames.
 
 
 
    
        New working platform layout ready for frame
    
        fitting
 
    
        The far section has been cover over as the
        restoration has been completed except for the
    
        new teak for the lower panels. 
 
    
        Preparation of the frame base ready for the
    
        new frames
 
    
        A very sorry looking luggage van
        doorpost
 
    
        March 13th  2012
    
        The frames are fitted.
 
 
 
 
    
        Trial Fitting of the expansion post for the passenger profile
 
 
 
 
    
        March 17th  2012
    
        The frames are fitted.
 
    
        Temporary lower plywood panel fitted, top teak
        panels are being prepared and will be fitted
    
        shortly along with the glass 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
    
        May 10th  2012
    
        Section R1 panelling is complete and section R2 is progressing well.
 
    
        July 21st/22nd  2012 (peep behind the scenes weekend)
    
        The covers are removed showing off the freshly varnished top panels on luggage end.
 
    
        And the first of the top panels fitted in to
    
        the new frames for the passenger end.
 
    
        View of the new frames from the inside.
 
 
    
        July 5th  2012
    
        The first of the passenger doors is hung.
 
    
        November 11th  2012
    
        Corridor glass, temporary drop lights and all top panels fitted, also luggage doors re-hung.
 
    
        On the inside the match boarding on the corridor side has been fitted, stained and the first coats of varnish applied.
 
    
        View looking towards the luggage
    
        end showing the match boarding.
 
    
        View looking towards the passenger end.
 
    
        The construction of the frames for the compartment side are underway.
 
    
        And a bit of before and after.
 
    
        View of the original end frames
    
        the condition is good.
 
    
        View of the rebuilt end frames
    
        now awaiting the panelling.
 
    
        March 13th  2012
    
        The frames are fitted.
 
 
 
 
    
        Trial Fitting of the expansion post for the passenger profile
 
 
 
 
    
        March 17th  2012
    
        The frames are fitted.
 
    
        Temporary lower plywood panel fitted, top teak
        panels are being prepared and will be fitted
    
        shortly along with the glass 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
    
        May 10th  2012
    
        Section R1 panelling is complete and section R2 is progressing well.
 
    
        July 21st/22nd  2012 (peep behind the scenes weekend)
    
        The covers are removed showing off the freshly varnished top panels on luggage end.
 
    
        And the first of the top panels fitted in to
    
        the new frames for the passenger end.
 
    
        View of the new frames from the inside.
 
 
    
        July 5th  2012
    
        The first of the passenger doors is hung.
 
    
        November 11th  2012
    
        Corridor glass, temporary drop lights and all top panels fitted, also luggage doors re-hung.
 
    
        On the inside the match boarding on the corridor side has been fitted, stained and the first coats of varnish applied.
 
    
        View looking towards the luggage
    
        end showing the match boarding.
 
    
        View looking towards the passenger end.
 
    
        View from the guards door looking towards the passenger end.
        Note: the door on the left a legacy from when the carriage was used as the funds shop!
 
    
        The construction of the frames for the compartment side are underway.
 
    
        And a bit of before and after.
 
    
        View of the original end frames
    
        the condition is good.
 
    
        View of the rebuilt end frames
    
        now awaiting the panelling.